Skip to main content

HB 560

AN ACT relating to light pollution mitigation for wind turbine generators.

House Bill
Filed

Filed

Bill introduced by legislator

Committee

Hearing

Passed Cmte

Calendar

Passed

Sent

Enrolled

Governor

Signed

89th Regular Session

Jan 14, 2025 - Jun 2, 2025 • Session ended

Awaiting Committee Assignment

Bill filed, pending referral to House committee

← Back to Bills

Committee

Not yet assigned

Fiscal Note

Not available

What This Bill Does

relating to light pollution mitigation for wind turbine generators.

Bill Text

relating to light pollution mitigation for wind turbine generators.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
SECTION 1.  Subchapter A, Chapter 35, Utilities Code, is
amended by adding Section 35.0023 to read as follows:
Sec. 35.0023.  WIND TURBINE LIGHT POLLUTION MITIGATION.  (a)
This section applies only to an electric utility, power generation
company, or exempt wholesale generator that:
(1)  is required by the Federal Aviation Administration
to use aviation obstruction lighting; and
(2)  sells at wholesale electric energy produced by a
(b)  The commission by rule shall require an electric
utility, power generation company, or exempt wholesale generator to
apply to the Federal Aviation Administration, or another applicable
federal entity, for authorization to install and operate technology
to mitigate light pollution from the wind turbine generator using a
light mitigation technology system.
(c)  The rules adopted under Subsection (b) must require an
electric utility, power generation company, or exempt wholesale
(1)  installs a wind turbine generator on or after
(A)  submit an application for approval of light
mitigation technology to the Federal Aviation Administration not
later than 180 days before the commercial operations date for the
(B)  install light mitigation technology on all
wind turbine generators not later than 18 months after receiving
approval of the technology from the Federal Aviation
(C)  if installation of the light mitigation
technology is delayed due to forces outside of the control of the
utility, company, or generator, make a quarterly report to the
commission detailing the reasons for the delay; or
(2)  installs a wind turbine generator before December
(A)  on repowering or not later than the 180th day
after the execution of a newly signed long-term power purchase
agreement, submit an application for approval of light mitigation
technology to the Federal Aviation Administration;
(B)  install light mitigation technology on all
wind turbine generators not later than 18 months after receiving
approval of the technology from the Federal Aviation
(C)  if installation of the light mitigation
technology is delayed due to forces outside of the control of the
utility, company, or generator, make a quarterly report to the
commission detailing the reasons for the delay.
(d)  Subsection (c) applies only to a wind turbine generator
with a commercial operations date that occurs after December 31,
(e)  Notwithstanding Section 15.023(b), the total amount of
an administrative penalty assessed for a violation continuing or
occurring on separate days under this section may not exceed $1
SECTION 2.  This Act takes effect September 1, 2025.

Bill History

filed

Bill filed: AN ACT relating to light pollution mitigation for wind turbine generators.